32. ENVIRONMENTAL

32.1 Obligations

An Operator shall perform the cartage work in accordance with any legislative and regulatory environmental requirements and Boral's environmental policy and procedures (provided that they have been inducted into the policy or procedure and provided with a copy of it). Responsibility and accountabilities of the Operator include but are not limited to the following, to:

(a) co-operate with any reasonable request made by the plant or site supervisor or manager to ensure compliance with the Environmental Act and Boral environmental policy;

(b) comply with the Clean Air Act 26(1), which refers to motor vehicles;

(c) prevent fresh concrete contaminating roadways and cement slurry entering stormwater drains by ensuring chutes are free of excess concrete or loose material prior to leaving the plant and job site;

(d) not washdown on site without the approval of the customer and only in areas designated by the customer;

(e) always wash out the mixer and discharge slurry into wash out pits or contained areas; and

(f) from time to time participate in meetings to, review and implement environmental procedures. The Operator will be paid for all time spent in relation to duties associated with these meetings in accordance with item (L) of Schedule 1. To avoid any doubt, during this time Boral will continue to pay the monthly retainer.