AN120154 – Concrete Pipe and Concrete Products Factories Consolidated (State) Award

TABLE 2 - OTHER RATES AND ALLOWANCES

Item No.

Clause No.

Brief Description

SWC 2004 Amount

SWC2005 Amount

     

$

$

         

1

8(viii)

Leading Hands in charge of -

   
   

2 employees

14.00

14.40

   

3-6 employees

18.50

19.05

   

more than 6 employees

22.20

22.85

2

8(i)

Industry allowance (other than the factories)

14.10 p/wk

14.50 p/wk

3

8(i)

Industry allowance for tile factories

9.20 p/wk

9.50 p/wk

4

8(ii)

Lumpers of cement/concrete articles

0.40 p/hr

0.41p/hr

5

8(ii)

Preparing/Applying epoxy based materials

0.55 p/hr

0.57 p/hr

6

8(iii)

Sand blasting

0.55 p/hr

0.57 p/hr

7

8(iv)

Working in the rain

0.19 p/hr

0.20 p/hr

8

8(v)

Bituminous preparations

0.40 p/hr

0.41 p/hr

9

8(vi)

Slurry work

1.18 p/day

1.22 p/day

10

8(vii)

Wet money

1.35 p/day

1.39 p/day

11

12(d)

Meal allowance

10.10 p/meal

10.40 p/meal

12

24(b)

First-aid

2.04 p/day

2.10 p/day

13

27(iv)(a)

Country work (7days)

274.50 p/wk

286.30 p/wk

14

27(iv)(b)

Country work (broken week)

39.20 p/night

40.90 p/night

15

31(a)(ii)

Clothing

1.58 p/wk

1.58p/wk

 

31(b)(ii)

Boots

1.99 p/wk

1.99 p/wk

16

Appendix 1

Fork lift Allowance

4.75 per week

4.90 per week

17

35

Loss of clothing - maximum of:

535.50

535.50

"Note": These allowances are contemporary for expense related allowances as at 30 March 2005 and for work related allowances are inclusive of adjustment in accordance with the June 2005 State Wage Case Decision of the Industrial Relations Commission of New South Wales.