[2013] FWC 5592

Download Word Document

FAIR WORK COMMISSION

DECISION


Fair Work Act 2009

s.739—Dispute resolution

Michael Stevens
v
Australian Federal Police
(C2013/3273)

Commonwealth employment

COMMISSIONER LEE

MELBOURNE, 15 AUGUST 2013

Application to deal with a dispute.

[1] On 25 February 2013 Mr. Michael Stevens (the Applicant) referred a dispute with Australian Federal Police (the Respondent) to the Fair Work Commission (the Commission) pursuant to the dispute settlement procedure contained in clause 70 of the Australian Federal Police Enterprise Agreement 2012-2016. This agreement will be referred to throughout this decision as the “New Agreement”.

[2] The matter also involved consideration of the terms of the Australia Federal Police Collective Agreement 2007-11. That agreement will be referred to throughout this decision as the “Old Agreement”

[3] The application lodged stated that the dispute related to clause 16 “Management Initiated Temporary Transfer”, Clause 58 “Redeployment and Redundancy” and Clause 59 “Termination of Employment” of the New Agreement. The Applicant alleges that the dispute involves the Respondent’s failing to agree to make the Applicant redundant and pay the Applicant his redundancy entitlements of 52 weeks severance pay, pursuant to clause 58(17)(d) of the New Agreement and the Respondent’s failure to pay notice period payment entitlements pursuant to clause 59 of the New Agreement.

Proceedings

[4] The dispute was initially dealt with in conciliation by Commissioner Lewin on 21 March 2013, however the conciliation failed to resolve the dispute. The matter was then allocated to me for arbitration.

[5] After a number of failed attempts to hold a mention/directions hearing in order to settle on the question to be determined in the arbitration, I wrote to the parties on 8 April 2013 and proposed a possible question to be determined in the arbitration. I framed the question based on the materials that had been filed by the Applicant. That question was;

[6] Mr. Matarazzo, acting on behalf of the Applicant replied on the morning of 9 April 2013 that the question to be determined should be as follows:

[7] Later in the day on 9 April 2013, Mr. Matarazzo advised that he sought a further change to the question to be determined. His further amended wording was as follows;

[8] Mr. Matarazzo stated that the “question is in essence what the dispute is about”. The Respondent advised by email on 10 April 2013 that they had no objection to the variations to the question sought by Mr. Matarazzo. I amended the question to be determined to reflect the change sought by Mr. Matarazzo, consented to by the Respondent, and sent out to the parties the amended question and directions for hearing the matter by way of a Statement on 10 April 2013.

[9] Notwithstanding the question to be determined reflecting the wishes of the Applicant, on the day of the hearing Mr. Matarazzo sought, to amend the question to refer to rights for redundancy under the New Agreement. 1 In effect, to return to the question that I originally framed. This last minute change on the part of the Applicant’s representative was difficult to comprehend given the process outlined above for setting the question to be determined. It also made the conduct of the proceedings more protracted than they needed to be and created a level of confusion for both the Respondent and the Commission. In any event, I have considered in determining this matter, whether or not the Applicant is or was entitled to voluntary or involuntary redundancy pay under either the Old Agreement or the New Agreement.

[10] The matter was set down for hearing on 13 May 2013 in Darwin. Mr Matarazzo sought and was granted permission to appear on behalf of the Applicant. Mr Will sought and was granted permission to appear on behalf of the Respondent. Evidence was given by the Applicant and Mr Edward Paul Williams gave evidence for the Respondent.

Background to dispute and chronology of events

[11] The Applicant was employed as a Protective Service Officer (PSO) at the Darwin International Airport. He commenced work there in March 1996. In June 2009 a Federal Audit of Police Capabilities was delivered by Mr. Roger Beale. The audit recommended that the Respondent change from the “Unified Policing Model” to a new “All in” model. The recommendation was accepted by the Federal Government in December 2009. Under the new model, all security and policing services at Australian airports are to be provided by Australian Federal Police members. “Project Macer” was set up in July 2010 to manage the transition to an all Australian Federal Police member model, and the phasing out of the role of PSOs at Australian Airports over a three to five year period. Approximately 600 PSOs at Australian Airports were affected by the change to this new model. 2 The Applicant was one of those affected.

[12] As a consequence of the change to the new model, the Applicant along with other PSOs was declared potentially “excess to requirements” on 27 May 2010. He along with other PSOs was advised by email that this was the case. The email referred to clause 33 of the Old Agreement indicating that the reason the roles were potentially excess was that, “the services of the employee cannot be effectively used because of technological or other changes in the method, or changes in the nature, extent or organisation of the functions of the AFP”. 3 The email included the following paragraph: “I appreciate that this notification may cause you some concern. I would like to reassure you that wherever possible the AFP will be seeking to support those who wish to become sworn officers...to make that transition or alternatively for those who do not wish to become sworn police officers, determining if there is a suitable redeployment option.”4

[13] On the next day, 28 May 2010, there was an email sent to the Applicant and all aviation staff, calling for expressions of interest for voluntary redundancy arising from the change to the “all in” model. 5 This email refers to the Respondent pursuing a policy of redeployment, reduction or redundancy, in accordance with the Old Agreement.

[14] The Applicant did not make an expression of interest in voluntary redundancy at that time. Rather, he chose to be redeployed into a sworn member policing role, by applying for a vacant position and accepting a position on the transitional training program. That offer was made on 11 October 2010. 6 The Applicant could still at that time have elected to take a voluntary redundancy but chose not to.7 Subsequently, the Applicant progressed successfully through the required several weeks of training in Canberra, attested as a sworn Australian Federal Police member and was declared a sworn member of the Australian Federal Police on 4 March 2011.8 The Applicant agreed to the revocation of his status as a PSO on 2 March 2011. His status as PSO was revoked on 3 March 2011. He was assigned to duties at Darwin Airport. The assignment notes that it had effect from 5 March 2011 to 31 December 9999 (i.e. an unspecified end date).9 At the time of the hearing, the Applicant was performing the role of an Australian Federal Police officer at Darwin Airport.

[15] Sometime after becoming a sworn officer of the Respondent, the Applicant determined that he did not enjoy the role of sworn member and sought a return to the role of a PSO. The Applicant first raised this request with the Respondent in late December 2011. The Respondent replied in January 2012 that his application to revert to PSO status was not possible in Darwin as there were no longer PSO positions in Darwin. 10 The Applicant was told that he could remain in his current role or place his name on the PSO redeployment register with a view to reverting to PSO status and taking a position in another location at his own expense.11

[16] The Applicant sent further correspondence to the Aviation executive of the Respondent on 11 May 2012. 12 In that correspondence, the Applicant again requested to revert to a PSO role. In the correspondence, the Applicant makes reference to reverting to a PSO as an “option” that the Respondent had made available in the “AFP Practical Guide on Project Macer PSO redeployment” (the Project Macer Practical Guide).13

[17] The Applicant received a reply from the Aviation Executive to his minute on 25 July 2012. 14 In that reply it was made clear by the Respondent that the request to revert to PSO status was rejected. The text of the reply minute from Mr. Williams - Manager Aviation Operations, was as follows:

[18] The Applicant then on 1 August 2012 wrote to Assistant Commissioner Leanne Close, the National Manager of Human Resources for the Respondent. Again, the Applicant sought a reversion to a PSO position referring to the “option that the AFP had made available in the [Project Macer Practical Guide]”. 15 Ms. Close replied to this correspondence on 30 October 2012, rejecting the Applicants claim to revert back to his former PSO role. Ms Close again stated that there were no longer PSO positions in Darwin. The option was provided to potentially revert to a PSO role, but that this would require moving geographic locations. Ms. Close indicated she would be happy to facilitate this where possible.16

[19] In these circumstances, the Applicant claims that he is entitled, within either the terms of the Old Agreement or the New Agreement, to be made redundant, either voluntarily or involuntarily. The chronology above demonstrates that the Project Macer Practical Guide is, from the Applicants perspective, an important consideration, along with other evidence led by the Applicant, in determining the question I must answer. The Applicant submits that there is the necessary jurisdiction to determine the dispute.

[20] The position of the Respondent is that the Applicant is not redundant and that redundancy payments can only be made when an employee is redundant. Further, the Respondent argues that that the provisions of clause 33 of the Old Agreement that deal with redeployment or reduction in classification are “legally and logically mutually exclusive” from the provisions that deal with redundancy. 17 The Respondent argues that the Applicant was excess to requirements in May 2010 and that in accordance with the terms of clause 33 of the Old Agreement, the Applicant was given the option of expressing an interest in redundancy or redeployment. Having chosen to be redeployed, the Respondent maintains that the Applicant cannot now be made redundant as the position to which he has been redeployed is not, in fact, redundant. In respect to the Project Macer Practical Guide the Respondent submits that it applies to any existing PSO intending to become an Australian Federal Police member, not to Australian Federal Police members and that it is not a mechanism whereby sworn members can revert to their former PSO role.18 The Respondent submits that there is no jurisdiction to determine the dispute.

The law to be applied

[21] This decision requires a consideration of the correct approach to the construction of the terms of enterprise agreements (in respect of the New Agreement) and transitional instruments (with respect to the Old Agreement). I recently canvassed the key authorities in my decision in National Union of Workers v Warehouse Solutions Pty Ltd 19 and for convenience I will in large measure reproduce them here.

[22] In a recent Full Bench decision of the Commission, Cape Australia Holdings Pty Ltd T/A Total Corrosion Control Pty Ltd v Construction, Forestry, Mining and Energy Union 20, the general approach to the construction of enterprise agreements was considered. The Full Bench stated that;

[23] The case at hand involves the consideration of extrinsic material. It is therefore important to consider the admissibility of such material and whether or not it is necessary to find ambiguity in the relevant instrument before it is admissible.

[24] In Watson v ACT Department of Disability Housing and Community Services 22, a decision of Vice President Lawler, it was held that;

[25] This approach was favourably referred to by the Full Bench in The Australian Workers’ Union v Co-operative Bulk Handling Limited 24 where it was stated that;

[26] This approach was consistent with the approach adopted by his Honour Marshall J in Australian Municipal, Administrative, Clerical and Services Union v The Treasurer (Cth) and others 26 where it was stated that;

[27] The following section the decision of Burchett J in Short v FW Hercus Pty Ltd 28 is relevant to a consideration of where a word or expression may be considered to be ambiguous, what it may mean.

[28] In my view, there is considerable authority to support an approach that allows for the admissibility of extrinsic material even in circumstances where ambiguity is not present. However such an approach does not allow a departure from the principles as they apply to the reliance on extrinsic material in Short v FW Hercus Pty Ltd 30. As described above, Marshall J in Australian Municipal, Administrative, Clerical and Services Union v The Treasurer (Cth) and others31 makes clear he is bound by those principles.

[29] Nor does recourse to extrinsic material allow a departure from the principles applying to construction as set out in Cape Australia Holdings Pty Ltd T/A Total Corrosion Control Pty Ltd v Construction, Forestry, Mining and Energy Union 32 already set out.

[30] I will apply these principles as relevant in this determination.

Jurisdiction

[31] Both parties provided written submissions on the question of jurisdiction. The Applicant contends that there is jurisdiction though the submissions from the Applicant’s representative on the issue were far from clear. The Respondent argued that there was no jurisdiction for the Fair Work Commission to determine the matter.

[32] The Respondent’s submissions helpfully and clearly set out the legal position on the powers of the Fair Work Commission to arbitrate disputes pursuant to the Act and I repeat and adopt them here.

[33] The primary issue is whether or not the dispute involves an exercise of the dispute settlement power in the New Agreement or the Old Agreement. It is not contested that the Applicant fell within the coverage of both the Old and the New Agreement. 33 That being the case, it is clear that having regard to the Transitional Provisions and Consequential Amendments Act 2009, that the Old agreement has been displaced by the New Agreement and has no legal effect.34 It follows that there is no power to arbitrate this matter under the dispute settlement clause of the Old Agreement as it no longer has legal effect.

[34] That determined, this dispute can only be determined (and only then if the other requirements for jurisdiction are satisfied) pursuant to the dispute settlement procedure contained in the New Agreement.

[35] A further requirement to allow jurisdiction to be exercised is whether or not the relevant steps in the dispute settlement procedure contained in the New Agreement have been followed. There is no jurisdiction for the Commission to determine a matter if the relevant steps in the dispute settlement procedure have not been followed. In this matter, that is not in contention. It was submitted by both parties that the relevant steps have been followed. The chronology above makes clear that the relevant steps were complied with.

[36] Consideration also needs to be given as to whether there is power to arbitrate under the dispute settling clause in the New Agreement. This leads to the basis of the jurisdictional objection of the Respondent which is rooted in clause 72(18) of the New Agreement. That clause is as follows:

[37] It was submitted by the Respondent at the hearing 35 and in their written submissions36 and not contested by Mr. Matarazzo, that the Applicant was an employee covered by both categories in sub clauses 72(18)(a) and (b) of the New Agreement. As it is clear that 72(18) applies to the Applicant, the Respondent points out that that this clause provides that the “redundancy provisions” of the Old Agreement apply to the Applicant. The Respondent in turn points out that the wording in clause 72(18) provides that the redundancy provisions apply “to the exclusion of the terms in the agreement.” The Respondent submits that this provision needs to be read together with the opening words of clause 70 which allows for the settlement of disputes about matters arising under this agreement.37

[38] It is submitted by the Respondent that the consequence of these provisions is that the present dispute, which is about the Applicant’s entitlement to redundancy pay under the Old Agreement, is not within the dispute resolution term set out in clause 70 of the New Agreement as that term is limited to disputes arising from the New Agreement. 38

[39] Mr. Mattarazzo for the Applicant asserted that the dispute settlement term should not be narrowly construed. 39

[40] I agree with the submissions of Mr. Matarazzo that the term “arising from the agreement” should not be narrowly construed. The words should be given their ordinary meaning. Clause 72(18) in the New Agreement clearly contemplates that a particular class or classification of employees is to be treated in a different manner to other employees in respect to redundancy. This is consistent with the submissions of Mr. Will, that it was “the fair thing to do”. 40 Clause 72(18) is unambiguously part of the New Agreement. In my view, in referring to the redundancy provisions of the Old Agreement as applying to the exclusion of the terms in the New Agreement, the New Agreement incorporates the redundancy provisions of the Old Agreement, for the relevant class of employees, as terms of the New Agreement.

[41] I do not accept the argument of Mr. Will for the Respondent that the dispute settlement procedures in the New Agreement do not apply to the Applicant because of the operation of clause 72(18). The logical extension of this argument is that none of the terms of the New Agreement apply to the Applicant or other employees within the scope of clause 72(18). Mr. Will for the Respondent initially claimed that the intent of those words was that all of the other terms, including the dispute settling terms, fall away. 41 He then clarified that he thought it was only the dispute resolution clause that doesn’t apply to them.42 His response to my question as to how one could pick out just that the dispute settlement clause as not applying was unclear.

[42] The words in clause 72(18) need to be given their ordinary meaning. They also need to be considered within the context of the New Agreement as a whole. A strictly literal interpretation of the words suggests that the redundancy provisions in the Old Agreement apply to the exclusion of all the terms of the New Agreement. However, the scope clause in clause 5 of the New Agreement makes clear that the New Agreement applies to all employees of the Respondent, with various exceptions noted. The Applicant does not fall within any of the exempted categories. The exemptions do not include employees covered by clause 72(18).

[43] There is no basis upon which it could be found, as submitted by the Respondent, that the words in clause 72(18) of the New Agreement operate to exclude only the dispute settling clause and not all the other terms. As a matter of construction, it seems the choice is to determine that all of the clauses in the New Agreement are excluded from their application to the Applicant and others in his category or alternately, it is only those terms that could be said to relate to redundancy that are excluded.

[44] In my view, it would indeed be an absurd and illogical outcome if the former interpretation were true. 43 It would mean that the Applicant and others in his category are excluded from all of the terms of the New Agreement. This is clearly a circumstance where illogical prose should be met with a generous approach to construction. To do otherwise would be to construe the agreement in a manner that was divorced from industrial realities. Accordingly, I determine that the proper construction of clause 72(18) is that it operates so as to exclude the redundancy terms in the New Agreement from application to employees falling into the categories of sub clauses 72(18) (a) and (b.) It follows that all of the other terms of the New Agreement, including the dispute settling terms, apply to the Applicant.

[45] It follows from the reasoning above that a dispute over the entitlement to redundancy arising from the application of the redundancy terms of the Old Agreement, is in fact “a matter arising” under the New Agreement, provided that the employee is in a category covered by clause 72(18) of the New Agreement. As the Applicant is in such a category, it follows that there is jurisdiction to determine the question posed within the limits of the dispute settling clause in the New Agreement.

[46] I therefore conclude that there is the necessary jurisdiction to determine the answer to the question as posed, under the terms of the dispute settling power in the New Agreement.

[47] I further note that it follows that there is no jurisdiction to determine the alternative position advanced by Mr. Matarazzo on the day of the hearing that the applicant is entitled to redundancy under the terms of the New Agreement. As the Applicant is covered by clause 72(18) of the New Agreement, he is excluded from the redundancy terms in the New Agreement.

[48] In light of my finding above it is not necessary to deal with the additional argument of the Respondent that the dispute settlement clause 47 of the Old Agreement is not a term of an “enterprise agreement” as provided for in section 738(b) of the Act. 44

Submissions and evidence

[49] The Applicant gave evidence on his own behalf. Mr. Burtenshaw also provided a statutory declaration for the Applicant. He did not appear as the Respondent did not seek to cross examine him. Mr. Williams gave evidence for the Respondent.

[50] Much of the history of this matter is uncontested and the chronology is set out above. Indeed, a great deal of the evidence of the Applicant goes to the chronology of events. Other evidence that was provided by the Applicant included:

[51] As detailed above, a statutory declaration was filed by Mr. Burtenshaw. Mr. Burtenshaw was also a student at the AFP course in Canberra when the Applicant was there. Mr Burtenshaw makes the claim in his declaration that: “To the best of my recollection we were informed that at any time during the MACER course or the following year after whilst we are completing our competency log books, we can if we choose to or if we are unable to complete the work book, revert back to our original positions of PSO’s from where we had come from”. Mr. Burtenshaw did not appear at the hearing.

[52] The evidence of Mr. Williams for the Respondent largely sets out the chronology of events and that has been dealt with above. Other matters raised in his evidence and relevant to the dispute include:

The Management Initiated Transfer issue

[53] The submission of the Applicant included the assertion that the employee was the subject of a “Management Initiated Transfer” (MIT), pursuant to clause 19.3 of the Old Agreement. There was no evidence to support the submission of the Applicant that this was an MIT within the meaning of that clause. Nor was it clear from the submissions of Mr. Matarazzo how, were it to be found to be applicable, that would impact on the question to be determined. In any event, I do not consider that the redeployment of the Applicant was an MIT within the meaning of that clause of the agreement. However, even if I am wrong on that point, I cannot see that it would have any bearing on my determination. The MIT clause provides an entitlement for a “base composite” to be paid or not paid, depending on the type of transfer. The MIT clause has no relationship or impact on the operation of clause 33 of the Old Agreement.

Consideration

Is the applicant entitled to redundancy under either the old or new agreement?

[54] As discussed above under jurisdiction, it is clear that the terms of clause 33 of the Old Agreement apply to the Applicant through the operation of clause 72(18) of the New Agreement. If there is a right to redundancy, it is through the application of that clause to the circumstances of the Applicant.

Does the applicant have a right to redundancy under clause 33 of the Old Agreement?

[55] The key matter for determination is the proper construction of clause 33 of the Old Agreement. I note that the Applicants’ representative did not provide any submissions particularly directed to this task, despite it being a fundamental aspect of the case. The Respondent’s submission on the proper construction of clause 33 are set out below;

[56] I agree with the construction of clause 33 advanced by the Respondent. It is consistent with the ordinary meaning of the words. The clause provides a process to be followed in circumstances where an employee is found to be excess to requirements. The Applicant was excess to requirements in May 2010. The evidence is that the Respondent followed the process in clause 33. The Applicant was provided with options to either express an interest in redundancy or retraining and redeployment for a position as a Australian Federal Police officer. There was a considerable period of time, between May and October 2010 between when the Applicant was declared excess to requirements and when he accepted the position on the training course. The Applicant’s evidence was that an option of applying for voluntary redundancy was available to him as late as October 2010.

[57] Ultimately, the process was completed. He is now a sworn Australian Federal Police officer. The terms of clause 33, assuming my construction of its terms are correct, was complied with. The Applicant is no longer excess to requirements. The unchallenged evidence of Mr. Edwards is that the Respondent is recruiting Australian Federal Police officers. To be clear, for an entitlement to redundancy to arise the Applicant must first be excess to requirements. Mr. Stevens is, on the uncontested evidence, not now excess to requirements.

Does the Applicant have a right to return to a PSO position?

[58] The submission of Mr. Matarazzo for the Applicant was essentially that the Applicant had a right to return to his, now abolished PSO position by virtue of the provisions of the Practical Guide to Project Macer, thus triggering rights to redundancy, under either the Old or New agreement. As a first point, I do not think that there is any such right within the terms of either clause. As said above, the clauses provide a process; that process was commenced, followed and completed. There is no right to return to the position that was abolished, that lead to the process commencing. Indeed, in my view this would be an absurd construction of the terms of either clause in the Old or New Agreement.

[59] The key argument of Mr. Matarazzo was that the right to return to a PSO position derives from the Project Macer Practical Guide itself. This requires a consideration of what the status of the Project Macer Practical Guide is. In his submissions, Mr. Matatarzzo said that the Project Macer Practical Guide had contractual force. 58 On the day of the hearing, Mr Matarazzo changed that submission and put the alternate submission that they were, “issued under the consultation clause of the enterprise agreement, as they are obliged to do”.59 He sought in the alternative to argue that they formed part of the consultation requirements arising under the terms of the agreement and therefore they could be considered as being incorporated into the terms of the agreement.60 There was no authority advanced for this proposition, no evidence led in support, nor was the argument developed. The Respondent submitted that there was not a basis to find the Project Macer Practical Guide was incorporated.61

[60] I agree with the submissions of the Respondent on this point. The Project Macer Practical Guide is not an incorporated term, into either the Old or the New Agreement. There is no evidence to support the view that it is an incorporated document. There is nothing in the Project Macer Practical Guide which suggests that it arises from an obligation under the Old or New agreement. The evidence of Mr. Williams was that it was issued as part of the Respondent’s professional standards framework. The Project Macer Practical Guide was issued by the National Manager Aviation using power under s.37(1) of the Australian Federal Police Act 1979. 62 It is clear that the Project Macer Practical Guide is a document that the Respondent chose to produce as part of implementing the scheme. They were not compelled to produce it through the operation of the consultation or any other clause.

[61] As indicated above, there is no basis to conclude the Project Macer Practical Guide is an incorporated term into either the Old or the New Agreement. As it does not form part of either agreement it cannot form the basis of an entitlement to voluntary or involuntary redundancy pay for the Applicant. It is therefore not necessary to consider the construction of the terms of the Project Macer Practical Guide as I am urged to do by Mr. Matarazzo.

[62] The status of the Project Macer Practical Guide is that of extrinsic material. It represents an attempt by the Respondent to set out the various processes to be followed in implementing “Project Macer” and how the processes relate to the obligations under the Old Agreement. Having considered the terms of the Project Macer Practical Guide I can understand that its terms may have lead to some confusion for the Applicant as to the operation of the scheme. The Project Macer Practical Guide clearly indicates that PSOs taking the option that the Applicant took, “to pursue a career in policing” had full access to clause 33 of the Old Agreement if they could not meet training or workbook requirements, or elected to return to their former PSO role. There is also the reference to the assignment to a policing role for an initial 12 month period. This particular paragraph is not clear and creates some ambiguity as to how long it would be that an employee taking this option would have to return to their former PSO role.

[63] The Respondent sought to remove this ambiguity in the “e news” update dated March 2012, which sought to clarify, “When you are no longer part of the Macer process”. 63 Taken together, the documents do not give rise to ambiguity as to the meaning of clause 33 of the Old Agreement.

[64] As already indicated, the terms of clause 33 of the Old Agreement are clear. They do not provide a right for the Applicant to return to a PSO position nor to be made redundant when excess to requirements. While the evidence demonstrates, particularly the Project Macer Practical Guide, that the Respondent provided some level of flexibility as to when the door closed on the option of switching back to the redundancy option for employees who had chosen to redeploy, they were not bound to do so by the terms of clause 33. Having done so, it is also reasonable that the Respondent, having allowed that flexibility, to set some limit as to when the option for redundancy is no longer available.

Conclusion

[65] There is no entitlement to voluntary or involuntary redundancy pay under the terms of the Old Agreement, where the employee is no longer excess to requirements.

[66] The Applicant was, at a point in time now past, excess to requirements. Under the terms of clause 33 of the Old Agreement, he was entitled to redeployment, reduction in classification or a redundancy process. The Applicant was redeployed to a position of a sworn police officer with the Australian Federal Police. As an Australian Federal Police officer, it is clear on the evidence that he is not excess to requirements. Therefore there is no entitlement to redundancy.

[67] In terms of the Project Macer Practical Guide, these are not incorporated terms and therefore do not provide an entitlement to either return to his old position and/or be made redundant. Therefore, they do not provide a basis for answering the question in the affirmative as the Applicant seeks me to do.

[68] As extrinsic material, the Project Macer Practical Guide can be considered, along with other extrinsic material, in considering the construction of the terms of clause 33 of the Old Agreement. However, clause 33 is clear in its terms. The options of redeployment, reduction in classification or redundancy appear to be, on the ordinary meaning of the words, mutually exclusive. 64 When all of the extrinsic material is considered together, it does not give rise to an ambiguity in Clause 33.

[69] It follows from the above reasoning that the answer to the question to be determined by me in this matter is no. Further and consistent with my reasoning above, the answer to the alternate question put by Mr. Matarazzo on the day of the hearing, “Is the applicant entitled to redundancy under the terms of the new agreement”, the answer is also no.

[70] I note that 70(11) states that parties to the dispute agree to be bound by a decision of FWA in accordance with this decision.

COMMISSIONER

Appearances:

L Matarrazzo for the Applicant

M Will for the Respondent

Hearing details:

2013

Darwin:

13 May

 1   PN82

 2   Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013, [4]

 3   See Attachment B to the Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013.

 4   Ibid

 5   Attachment C to the Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013.

 6   Attachment E to the Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013.

 7   PN340-348

 8   Attachment H to the Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013.

 9   Ibid

 10   Exhibit 6 to the Statutory Declaration of Mr Michael John Stevens dated 21 April 2013

 11   Ibid

 12   Exhibit 8 to the Statutory Declaration of Mr Michael John Stevens dated 21 April 2013

 13   Ibid

 14   Exhibit 9 to the Statutory Declaration of Mr Michael John Stevens dated 21 April 2013

 15   Exhibit 10 to the Statutory Declaration of Mr Michael John Stevens dated 21 April 2013

 16   Exhibit 13 to the Statutory Declaration of Mr Michael John Stevens dated 21 April 2013

 17   Respondent’s submissions, filed 7 May 2013, [4]

 18   Respondent’s submissions, filed 7 May 2013, [13]

 19   PR537358

 20   [2012] FWAFB 3994

 21   Cape Australia Holdings Pty Ltd T/A Total Corrosion Control Pty Ltd v Construction, Forestry, Mining and Energy Union [2012] FWAFB 3994, [7] - [9]

 22   [2008] AIRC 291

 23   Watson v ACT Department of Disability Housing and Community Services, [2008] AIRC 291, [15]

 24   [2010] FWAFB 4801

 25   The Australian Workers’ Union v Co-operative Bulk Handling Limited, [2010] FWAFB 4801, [14]

 26   (1998) 80 IR 345

 27   Australian Municipal, Administrative, Clerical and Services Union v The Treasurer (Cth) and others, (1998) 80 IR 345 at 347

 28   (1993) 40 FCR 511

 29   Short v FW Hercus Pty Limited (1993) 40 FCR 511 at 518

 30   (1993) 40 FCR 511

 31   (1998) 80 IR 345

 32   [2012] FWAFB 3994

 33   PN125-140

 34   Transport Workers Union of Australia v Coles Supermarkets Australia Pty Ltd, Ross J, O’Callaghan SDP, Lee C, PR533145

 35   PN174

 36   Respondent’s submissions on jurisdiction, filed 12 May 2013, [11]-[12]

 37   PN624

 38   Respondent’s submissions on jurisdiction, filed 12 May 2013, [14]

 39   PN87-89. See Shop, Distributive and Allied Employees Association v Big W Discount Department Stores PR924554

 40   PN196

 41   PN619-620

 42   PN626

 43   City of Wanneroo v Australian Municipal, Administrative, Clerical and Services Union (2006) 153 IR 426

 44   Respondent’s submissions on jurisdiction, filed 12 May 2013, [16]

 45   Statutory Declaration of Mr Michael John Stevens dated 21 April 2013, [2]

 46   Statutory Declaration of Mr Michael John Stevens dated 21 April 2013, [4]

 47   Ibid

 48   PN342-348

 49   Statutory Declaration of Mr Michael John Stevens dated 21 April 2013, [4]

 50   Ibid

 51   Ibid

 52   PN255

 53   PN399

 54   PN288

 55   Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013, [1] - [2]

 56   Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013, [9]

 57   Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013, [21]

 58   Submissions on behalf of the Applicant, filed 22 April 2013, [24] and [44]

 59   PN755

 60   PN764-765

 61   PN776

 62   Exhibit 2 to the Statutory Declaration of Mr Michael John Stevens dated 21 April 2013, the AFP Practical Guide on Project Macer PSO redelopyment, [4]

 63   Attachment L to the Statutory Declaration of Mr Edward Paul Williams, dated 6 May 2013

 64   City of Wanneroo v Australian Municipal, Administrative, Clerical and Services Union (2006) 153 IR 426

Printed by authority of the Commonwealth Government Printer

<Price code C, AE891991  PR540074>