14.1 Installation Of Communication Equipment
An Operator shall agree to the installation of two way radio and any other communication equipment required by Boral in or on their vehicle. All equipment shall be installed by Boral's approved technician and such installation shall be of a professional standard. The installation shall include all necessary equipment and the complete installation shall be undertaken at no cost to an Operator. Such equipment is to be positioned to an Operator's reasonable satisfaction.
14.2 Removal Of Communication Equipment
When such communication equipment is removed Boral shall make good the bodywork.
14.3 Taking Care Of The Communication Equipment
An Operator shall take due care to ensure adequate protection of the communication equipment but shall not be liable for any theft of it while the vehicle is in a Boral plant or any other approved location.
14.4 Operation Of Communication Equipment
The communication equipment is to be properly operated by Operators and appropriate procedures are to be followed as determined by Boral following the undertaking of any relevant training (which should be undertaken during working hours where practicable).
14.5 Maintenance Of Communication Equipment
Boral shall be responsible for the maintenance of the two way radio and other communication equipment.
14.6 Installation And Removal During Normal Operating Hours
Installation or removal of communication equipment will be carried out during normal working hours or at times agreeable to both parties.