AN120071 – Boral Resources (NSW) Pty Limited Sydney Metropolitan Concrete Contract Determination
Item |
Description |
Unit |
Six Wheeler |
Eight Wheeler |
$ |
$ | |||
A |
Retainer |
Per Month |
5,691 |
6,285 |
B |
Load Fee |
Per Load |
21.04 |
24.19 |
C |
Kilometre Rate |
Per KM |
1.90 |
2.16 |
D |
Mixing In Yard |
Per Load |
21.24 |
24.21 |
E |
Waiting Time |
Per Minute |
1.02 |
1.16 |
F |
Transfer Fee |
Per KM |
0.95 |
1.08 |
G |
Standby Time |
Per Half Hour |
14.89 |
15.60 |
H |
Out of Hours Surcharge |
Per Load |
29.78 |
31.20 |
(Monday -Saturday) |
||||
I |
Own Mixer Rate |
Per Load |
10.00 |
12.00 |
J |
Agitating Fee |
Per Minute |
1.02 |
1.16 |
K |
Car Travelling |
Per KM |
0.68 |
0.68 |
L |
Labour Hire |
Per Hour |
14.89 |
15.60 |
M |
Out of Hours Surcharge |
Per Load |
37.23 |
39.00 |
(Sunday Public Hol) |
||||
N |
Call Out Fee |
Fee |
119.12 |
124.80 |